The Accountant General (Audit)-I Maharashtra has pulled up the BrihanMumbai Municipal Corporation for certain lapses and irregularities in a Special Audit of 76 identified works worth Rs 12,000 crore - though Covid-19 management expenditure could not be audited due to non-cooperation of the civic body.
The audited works, covering nine key BMC departments, were for the period November 28, 2019 - the day when Maha Vikas Aghadi and Shiv Sena leader Uddhav Thackeray took oath as Chief Minister till October 31, 2022.
Ordered on October 31, 2022 by the new government headed by Chief Minister Eknath Shinde, the audit also included the expenditure on 13 Jumbo Covid Centres, 24 ward offices, five major hospitals, six specialised hospitals, 17 peripheral hospitals, one dental hospital and others.
However, the BMC had questioned the move to audit any acts/works/decisions taken for Covid management/expenditure of Rs 3,538.73 crore, referring to the Epidemic Act, 1897 and Disaster Management Act, 2005, and despite many reminders, didn't produce records related to the pandemic handling.
On the other aspects, the Audit frowned at awarding 20 works in two departments worth Rs 214.48 crore without inviting tenders, 64 works costing Rs 4755.94 in five departments had no agreements between the contractors and BMC, in 13 works costing Rs 3,355.57 crore in three departments, third party auditors were no appointed for quality control on the contractors.
Owing to these lapses, the BMC would not be able to take any legal action against the contractors who defaulted, showed scant respect for procedures and a weak internal control mechanism, systemic problems, poor planning and careless use of public funds, leading to lack of transparency in such big works.
Owing to several flaws in the systems and huge delays since December 2011, the Development Plan Department Chief Engineer overvalued by Rs 205.15 crore the acquisition of a 32,395 sqm plot of land in Eksar Village, Dahisar for public purposes.
The final award of Rs 349.14 crore was made in February 2020 and the Audit found that owing to the 8-year delay, the cost on this fully encroached plot increased by a whopping 716 percent based on the 2011 evaluation of the BMC, and even this award was higher by Rs 206.16 crore due to various reasons.
Now, the BMC would have to spend another Rs 77.80 crore on removing the encroachments and rehabilitating them, which also could shoot up with passage of time.
The audit has pointed at "undue favour" of Rs 27.14 crore to a contractor in the road over bridges contract on Dr E. Moses Road and Keshavrao Khade Marg, and a massive cost escalation from Rs 4,500 crore to Rs 6,322 crore in building two flyovers and an elevated rotary road on the Goregaon Mulund Link Road (GMLR).
The two ROBs had issues like extra items of work without approval, non-obtaining the technical sanction of the Competent Authority, non-submission of the agreement to BMC in handing over the Right of Way and frequent changes in the designs.
Accordingly, the work was delayed and of the two ROBs work on only one had started which was just 10 per cent completed till October 31, 2022 - against the target of achieving 50 per cent by mid-March 2022.
For the GMLR project, the work on a 4.7 kms long twin-tunnel, two flyovers and an elevated rotary road could have not started as the forest clearance is awaited since the BMC has not complied to conditions for the same though five years have lapsed since the proposal was made.
This has spiked the cost of the entire project from Rs 4,500 crore in Jan. 2019 to Rs 6,322 crore in Aug. 2022, plus the BMC prequalified a contractor for the work without verifying his experience credentials, and the Audit sought to fix the responsibility for the same.
On the structural auditor's recommendation to reconstruct the Gokhale Bridge in Andheri, the Audit found that the BMC junked it and instead went for certain repairs/strengthening works costing Rs 9.19 crore and that too without issuing tender, and later ended up making an aexcess payment' of Rs 1.99 crore to the Western Railway.
The BMC appointed an aineligible bidder' for building the Rs 464.72 crore Influent Pumping Station in Malad, violating tender conditions, said the Audit.
Since October 2016, poor monitoring and delays in getting clearances dogs a Waste-to-Energy Project costing Rs 648 crore, for the project of 3,000 ton per day capacity which was later cut down to 600 tons per day.
The contract was given in August 2022 for Rs 648 crore and so far Rs 49.12 crore has been paid, but the progress of the work till December 2022 is only 10 per cent.
The Audit has also found lapses, shortcomings, delays, irregularities, etc in the IT Department which saw a purported aloss' of Rs 37.68 crore, the tender-less works worth Rs 54.53 crore given to contractors for road works, of the 56 works examined, with irregularities in 51 works.
As work on hostel building for KEM Hospital was taken up without the Collector's permission, in the Acworth Municipal Hospital campus, there was a liability of Rs 2.70 crore as penalty, besides violation of tender conditions and Centre's directives on the redevelopment of the LTMG Sion Hospital.
In September 2019, the BMC awarded irregularly four works to improve the Mithi River within 24 months, but owing to various problems, there is a liability of Rs 19.42 crore on it, said the 146-pager Audit.
Established in 1873, the BMC administers an area of 480 sq.km. through three divisions, seven zones and 24 Wards, that makes up the country's commercial capital.
73rd B.N. Mullik Memorial All India Police Football Championship begins, CM lauds Police's role
Tripura Chief Minister Prof. Dr. Manik Saha today lauded the role of Tripura Police in carrying out various social activities, apart from significantly improving the state's law and order situation.
Tripura to create, fill up 333 posts in various departments
The Tripura Government has announced plans to create and fill up 333 posts across multiple state departments. The decision was taken during a recent cabinet meeting and was revealed by Cabinet Spokesperson Sushanta Chowdhury at a press conference on Monday.
Explosions near Russian Consulate in France have signs of terrorist attack: Moscow
The Russian Foreign Ministry on Monday stated that explosions on the territory of the Russian Consulate General in France's Marseilles resemble a terrorist attack.
Air Force Base in Bangladesh attacked, several injured
In a major incident of lawlessness that is currently prevailing in Bangladesh under the interim government led by Chief Advisor Mohammad Yunus, several miscreants launched an ambush attack on an Air Force Base in Cox's Bazar on the southeast coast of the country.
Indian tech industry to hit $300 bn revenue in FY26, workforce to reach 5.8 mn in FY25
The Indian tech industry is projected to reach $300 billion revenue in FY26, a Nasscom report said on Monday, adding that in the current fiscal (estimated), the industry will add at least 126,000 net new employees, taking the total workforce to 5.8 million.
Telangana tunnel collapse: L&T teams with advanced equipment join rescue operation
Two teams of construction major Larsen & Toubro with advanced equipment on Monday joined the operation to rescue eight trapped workers from an under-construction tunnel, a portion of which collapsed on February 22 in Telangana’s Nagarkurnool district.
Right time to invest in Madhya Pradesh: PM Modi at Global Investors Summit
Prime Minister Narendra Modi on Monday inaugurated the Global Investors Summit here highlighting investment opportunities in Madhya Pradesh and urging investors to tap available potential in the state.
Govt backs India Inc. bid to become major exporter of power equipment
India is on the path to becoming a major exporter of power equipment, with global players showing strong interest in the country’s domestic manufacturing capabilities, Secretary, Ministry of Power, Pankaj Agarwal has said.