The welding of the main coolant pipeline at the upcoming third 1,000 MW atomic power plant at Tamil Nadu's Kudankulam got completed early this month, Russia’s integrated nuclear power major Rosatom said on Friday.
According to Rosatom, the welding of the main coolant pipeline which began in December 2022, was completed on August 5.
The main coolant pipeline combines the main equipment of the primary circuit, including the reactor, the steam generators, and the reactor coolant pumps. Considering high requirements for quality and operational conditions, the main coolant pipeline welding is one of the most complicated and important stages of civil and erection works at the power unit.
"It is the reactor coolant pipeline that carries the water heated in the reactor into the steam generators from which the generated steam goes into the turbine steam path, and the turbine generator generates electricity," Rosatom said.
The Russian company said the main coolant pipeline has a total length of about 140 m, the thickness of the pipe walls is 70 mm, and the total length of 28 welded joints is more than 87 m. Its design service life is 60 years in a tough environment.
During the welding of the main coolant pipeline which began in December 2022, a technology proposed by the Russian party was used, which made it possible for the Nuclear Power Corporation of India Ltd (NPCIL) to reduce the operation time from 270 to 219 days.
Upon completion of the main coolant pipeline welding, "flushing with the open reactor" operations and the "hydraulic tests and circulation flushing of the primary circuit" stage will start, Rosatom added.
India's atomic power plant operator NPCIL has two functional 1,000 MW plants (Units 1 and 2) at Kudankulam, while four more (Units 3, 4, 5 and 6) are under construction. All the six units are built with Russian technology and equipment supplied by Rosatom.
Major equipment for building the third and fourth units have reached Kudankulam from Russia, while a sizable number of components for the fifth and sixth units are to come.
Govt targets to make Tripura self-reliant in fish production: Minister Sudhangshu Das
The state fishery minister Sudhangshu Das on Tuesday said that the government has targeted to make the state self-reliant in fish production and accordingly the government has taken multifaceted initiative to boost fish production in the state.
Tourism to bring alternative economy for Tripura: Sushanta in Assembly
The state tourism minister Sushanta Chowdhury on Tuesday said that the tourism sector in the state will be the backbone of the alternative economy in the coming days. Economic and social development of the local people will be achieved through this industry, he added.
Rs. 24.46 Cr provides as aid to flood-affected farmers: Ratan
In response to an unstarred question by MLA Sudeep Sarkar, Agriculture Minister Ratan Lal Nath revealed comprehensive details about the arrangements made by the Farmers Welfare Department to assist flood-affected farmers in the state.
Infra development of Rs 1000 Crore for rural schools underway: CM
Chief Minister Prof. Dr. Manik Saha today informed that for the development of educational infrastructure in rural areas, works amounting to approximately Rs 1000 crore are underway under various schemes.
5,520 drug users receive treatment, 612 recovers: Chief Minister
Chief Minister Prof. Dr. Manik Saha today informed that as of January 2025, a total of 5,520 injection drug users have received services from Opioid Substitution Therapy (OST) centers. Of these, 612 have completed treatment and returned to the mainstream of healthy, normal lives.
Pradyot slams Yunus’s statement on NE, urges Centre to take firm stance
Pradyot Kishore Manikya Debbarma, the Royal Scion and founder of the Tipra Motha Party, strongly condemned a recent remark by Muhammad Yunus, Bangladesh's Chief Advisor, regarding the Northeast Indian states, urging India to take a firm stance in response.
95 percent of Agartala Smart City works completed: CM
Chief Minister Prof. Dr. Manik Saha today informed that almost 95 percent of the work under Agartala Smart City Limited has already been completed and remaining works are expected to be completed by May 2025.
More relief, medical supplies: India continues humanitarian aid to Myanmar
In a heartwarming gesture, Myo Aung, the Chief Minister of Mandalay, visited the facility, witnessing first hand the compassionate care being extended. The Indian Army shared this on X on Tuesday with a few photos.