The much-anticipated but hugely-delayed Mumbai-Ahmedabad Bullet Train has yet to pick up speed, as the last fiscal ended.
The mega-venture, which will be the country's first Bullet Train -- in the making since over five years now -- has achieved just 30.15 per cent overall physical progress till March 31, as per official figures.
On the Gujarat side, the progress is a little over one-third -- 35.23 percent done; and on the Maharashtra side it's a dismal 19.65 per cent overall completed.
Around 56.34 of the civil works on the project has been achieved and pile work has been carried out on 272.89 km so far.
While pier work is done on 170.56 km, 45.40 km of girders have been launched so far, the Ministry of Railways (MoR) said recently.
India's maiden Mumbai-Ahmedabad High Speed Rail project (MAHSR) or Bullet Train, estimated to cost around Rs 108,000-crore, has been targeted for a trial run between Surat-Bilimora (63 km) by August 2026.
The entire 508 km-long Mumbai-Ahmedabad corridor -- comprising 156 km in Maharashtra and 352 km in Gujarat -- is likely to commence full operations only by 2027.
As per the National High Speed Rail Corporation Ltd. (NHSRCL), the Bullet Train would zoom at a maximum speed of 320 kmph, and the entire distance between Mumbai-Ahmedabad can be covered in just 127 minutes.
The MAHSR comprises 92 per cent high-speed elevated railway tracks through viaducts (total 460 km) and bridges (9.22 km), tunnels (25.87 km ), embankments/cutting (12.9 km).
A major highlight will be the rail corridor passing through the eco-sensitive Thane Creek between Mumbai-Thane on the northern side, a significant part comprising Thane Creek Flamingo Sanctuary (TCFS) which was designated as a Ramsar Site in August 2022.
To avoid disturbing the flamingos at the TCFS location and other wildlife in the adjoining rich mangroves, the MAHSR corridor will pass through an undersea tunnel at this sector.
It will be India's first undersea tunnel and the country's longest rail transport thoroughfare with a single tube of 13.2 metres diameters, as per MAHSR.
Starting from the Bandra Kurla Complex, the Bullet Train will zoom to the end destination, the Sabarmati Station of Ahmedabad.
It will zip through eight districts of Gujarat, three in Maharashtra, and the Union Territory of Dadra & Nagar Haveli and Daman & Diu en route.
The MAHSR would have halts at a dozen stations on its dizzying journey -- Mumbai-BKC, Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati.
73rd B.N. Mullik Memorial All India Police Football Championship begins, CM lauds Police's role
Tripura Chief Minister Prof. Dr. Manik Saha today lauded the role of Tripura Police in carrying out various social activities, apart from significantly improving the state's law and order situation.
Tripura to create, fill up 333 posts in various departments
The Tripura Government has announced plans to create and fill up 333 posts across multiple state departments. The decision was taken during a recent cabinet meeting and was revealed by Cabinet Spokesperson Sushanta Chowdhury at a press conference on Monday.
Explosions near Russian Consulate in France have signs of terrorist attack: Moscow
The Russian Foreign Ministry on Monday stated that explosions on the territory of the Russian Consulate General in France's Marseilles resemble a terrorist attack.
Air Force Base in Bangladesh attacked, several injured
In a major incident of lawlessness that is currently prevailing in Bangladesh under the interim government led by Chief Advisor Mohammad Yunus, several miscreants launched an ambush attack on an Air Force Base in Cox's Bazar on the southeast coast of the country.
Indian tech industry to hit $300 bn revenue in FY26, workforce to reach 5.8 mn in FY25
The Indian tech industry is projected to reach $300 billion revenue in FY26, a Nasscom report said on Monday, adding that in the current fiscal (estimated), the industry will add at least 126,000 net new employees, taking the total workforce to 5.8 million.
Telangana tunnel collapse: L&T teams with advanced equipment join rescue operation
Two teams of construction major Larsen & Toubro with advanced equipment on Monday joined the operation to rescue eight trapped workers from an under-construction tunnel, a portion of which collapsed on February 22 in Telangana’s Nagarkurnool district.
Right time to invest in Madhya Pradesh: PM Modi at Global Investors Summit
Prime Minister Narendra Modi on Monday inaugurated the Global Investors Summit here highlighting investment opportunities in Madhya Pradesh and urging investors to tap available potential in the state.
Govt backs India Inc. bid to become major exporter of power equipment
India is on the path to becoming a major exporter of power equipment, with global players showing strong interest in the country’s domestic manufacturing capabilities, Secretary, Ministry of Power, Pankaj Agarwal has said.